FEATURE – Oakmont Central Area Complex Redevelopment Project: Years of Discussion and Planning
After more than a decade of community discussions, committee work, and planning, the Oakmont Village Association (OVA) continues to evaluate a major redesign of the Central Complex—an evolving vision that has most recently culminated in Concept 3: “A Walk in the Park.” The project remains in its concept cost modeling phase, with discussions focusing on potential expansion, new facilities, and long-term sustainability for one of Northern California’s largest active adult communities. Simultaneously, OVA General Manager Christel Antone is leading a comprehensive facilities study to assess Oakmont’s current infrastructure needs.
A Long History of Planning and Proposals
The effort to reimagine Oakmont’s Central Complex is built on years of studies, committee reports, and planning efforts and understanding the Berger Center planning history is important.
- 2015: BIC-Berger Options Report
- Outlined five options for modernizing or rebuilding the Berger Center.
- Recommended Option 4 – Modernize & Expand, estimating a cost range of $2.6M to $3.1M.
- Emphasized the importance of flexibility and community needs in design.
- 2017: BAC Progress Report
- Addressed fire protection (sprinklers), earthquake remediation, and HVAC replacement.
- Identified the need for a lobby expansion and structural upgrades.
- Earthquake fixes have been completed, but HVAC and sprinklers remain linked for future upgrades.
- February 2018: Board Approval of Berger Upgrade Plan
- Approved a $4 million upgrade plan.
- Plan included expanding event space, upgrading infrastructure, and compliance with safety standards.
- Never implemented due to subsequent Board transitions and priorities. A Berger “refresh” was instead implemented with new flooring, kitchen update and basic maintenance upgrades.

- 2019: The Long-Range Planning Committee (LRPC) compiled resident input and recommended hiring professional architects to develop more substantial redevelopment and conceptual site plans.
- 2020: The Central Complex Committee (CCC) was formed to study potential renovations and expansions, later evolving into the Oakmont 2030 project, a long-term strategic initiative focused on community engagement and infrastructure evaluation.
- 2021–2023: The Oakmont 2030 project adopted the American Institute of Architects (AIA) Community Conversations model, designed to gather resident input through structured dialogues and collaborative visioning exercises.
Community Conversations and the 14-Item Project List
Using the AIA model, a series of in-person and Zoom meetings were held to identify community priorities for the Central Complex. These self-selected discussion groups were not a randomized or representative sampling of Oakmont’s membership. Despite extensive advertising and outreach efforts, only 16% of Oakmont members participated in the community conversations.
Key themes from these discussions included:
- Space utilization and accessibility,
- Sustainability and infrastructure needs,
- Enhancing Oakmont’s social and recreational amenities.
The Oakmont 2030 Working Group used this input to develop a 14-item project list (August 2023), which outlined major proposals, including:
- Expanding event and meeting spaces
- Constructing new buildings,
- Enhancing fitness and recreation facilities,
- Repurposing underutilized spaces,
- Creating more outdoor gathering areas.
This 14-item list became the foundation for the ArchiLOGIX conceptual designs later presented to the community.
Lack of Independent Financial Analysis and Comprehensive Membership Survey
It is important to note that during the Oakmont 2030 project process:
- No independent financial analysis was conducted to determine OVA’s financial capacity to undertake large-scale redevelopment in the short or long term.
- No membership-wide written questionnaire or preference survey—either mailed or conducted online—was completed to formally assess community-wide opinion.
- Instead, resident input was gathered exclusively through the 2030 Conversations, comment cards, user groups and a club survey. Conversations were led by a paid consultant facilitator.
Architect Mitch Conner of ArchiLOGIX, who also served as a consultant, attended meetings and helped synthesize resident feedback into the final 14-item project list, which ultimately shaped the three conceptual site plans presented to the community.
On December 19, 2023, the OVA Board of Directors unanimously approved a resolution to engage ArchiLOGIX, a professional architectural and planning firm, to begin the next phase of Central Complex planning. The resolution authorized ArchiLOGIX to develop three conceptual site plans, conduct a parking and ADA accessibility study, and coordinate with the City of Santa Rosa regarding regulatory considerations. It also included cost modeling for each design concept and permitted collaboration with a general contractor or cost consultant, if needed, to develop more refined estimates. This marked a significant step forward in transitioning from visioning and committee-led discussion to professional, data-informed analysis of redevelopment options. The Board emphasized that this engagement was preliminary in nature and intended to support future evaluation and community input, not to approve construction.
Community Engagement and Concept Refinement
User Groups: Formation and Purpose
As part of the Oakmont 2030 project process, User Groups were formed in March 2024 to help refine the preliminary Central Complex concept plans developed by ArchiLOGIX. These groups consisted of Oakmont members and staff who actively used different community spaces and could provide practical insights into how facilities should be expanded, repurposed, or modernized. Their role was to ensure that the designs aligned with resident needs before moving forward with cost modeling analysis and feasibility studies. The groups were organized into six key areas: Fitness, Indoor Gatherings, Education and Arts, Outdoor Gatherings, Walkability, and OVA Administration. Each group was tasked with evaluating specific functions and space requirements within the Central Complex and providing recommendations based on current and future needs.
User Group Contributions and Outcomes
User Groups conducted meetings, walkthroughs, and discussions to assess how existing spaces were used and what improvements were necessary. Their findings helped refine the 14-item project list originally created by the Oakmont 2030 Working Group and informed the modifications to Concept 3: “A Walk in the Park.” The Fitness User Group, for example, highlighted the need for expanded exercise facilities and improved accessibility, while the Indoor Gatherings Group emphasized the importance of additional meeting rooms. The Walkability Group focused on outdoor pathways, seating, and shaded areas, ensuring accessibility and usability for all residents. These refinements played a significant role in shaping the master plan concepts, which were then presented to the OVA Board and the broader community during the June 2024 Town Hall.
June 27, 2024: Town Hall Meeting
A Town Hall meeting introduced three conceptual site plans, each presenting different approaches to renovation, expansion, and new construction.
July 8–26, 2024: Comment Cards and Resident Feedback
Residents were invited to submit feedback on the three ArchiLOGIX conceptual site plans through comment cards available at the CAC and online. However:
- No mailed and online membership-wide survey was conducted to collect community wide quantifiable community preferences and sentiment analysis.
- Members of the Long-Term Planning Committee reviewed the comment cards and summarized their findings to the OVA Board.
September 19, 2024: Board Votes to Further Explore Concept 3
The OVA Board voted unanimously to continue evaluating Concept 3: “A Walk in the Park”, while emphasizing that this did not commit to construction. Instead, the vote authorized further cost modeling analysis and feasibility studies in collaboration with ArchiLOGIX and the OVA General Contractor.
Concept 3: “A Walk in the Park” – Proposed Improvements
Concept 3 (see article lead image) includes:
- A New Two-Story Fitness and Administration Building – Housing an expanded fitness center and OVA offices.
- Expansion of the Berger Center – Enlarging the auditorium, stage, storage, and lobby.
- Renovations to the Central Activity Center (CAC) – Adding meeting rooms, expanding the library, and relocating arts & crafts spaces.
- Outdoor Enhancements – Including a new pool, expanded lawn bowling and petanque areas, picnic spaces, and improved walking paths.
- New Maintenance Building – Relocating OVA maintenance operations to a new facility.
Clarifications on Cost Estimates and Decision-Making: March 2025
Recent communications from OVA leadership have addressed membership questions regarding financial considerations and the project’s current phase:
- Director Matt Oliver clarified that no comprehensive cost report has been received from Archilogix, the architecture and planning firm involved in the project. While some initial estimates have been shared with the OVA Board, they are considered preliminary and are not detailed enough to support Board discussion or decision-making.
- General Manager Christel Antone explained that the Archilogix agreement allows for hiring a cost consultant or general contractor if the Board chooses to explore specific aspects of a project in greater detail. However, no additional spending beyond the existing agreement has been approved. The collaboration between Nordby Construction and OVA is not formalized under an OVA-funded agreement but continues under the scope of Archilogix’s engagement.
Key Challenges Moving Forward
- Financial Planning
- A comprehensive cost modeling analysis must be presented to the membership once completed by the board. A facilities maintenance review report is also pending completion by the General Manager.
- The Board must determine whether loans and/or reserve funds will be authorized for buildouts.
- Project Scope Adjustments
- The feasibility of a phased approach may need further discussion.
- Elements of Concept 3 may require modification due to financial constraints.
- Community Involvement
- Only 16% of the OVA membership participated in AIA Community Conversations.
- No full community-wide survey has been conducted to quantify preferences.
- The Board has not committed to a membership referendum vote before adopting a redevelopment plan.
What Comes Next?
As of March 2025, the Central Complex redevelopment remains in the concept cost modeling phase. The OVA Board has not committed to construction or funding decisions, and no methodology has been approved for gathering quantifiable community-wide membership input.
The next steps will depend on financial feasibility, community sentiment, and Board priorities. Whether the project moves forward, is phased, or abandoned entirely remains to be seen. For now, Concept 3: “A Walk in the Park” remains under review, and the discussion continues.
References
Central Complex Report Final 2030 Report:
OVA Board Agendas and Packets with Attachments
https://oakmontvillage.com/article/category/board/agendas-board
OVA Town Hall Videos:
https://oakmontvillage.com/article/category/vid
OVA Announcements and ArchiLOGIX Concepts:
https://oakmontvillage.com/?s=Concepts+&id=56818
Here’s the AI definition of “paralysis by analysis”, sound familiar? “Analysis paralysis, or paralysis by analysis, occurs when overthinking and over-analyzing a situation prevents an individual or group from making a decision or taking action within a reasonable timeframe.”
What is the total amount spent on all these studies over the years?
I have now been asked by OVA administration not to quote the actual figures paid to consultants in contractual relationships here because people that are not members have access to this site. You can sign into the OVA website as a member and review the ArchiLOGIX contract and the board resolution that authorized payment. Separately would be the authorization for 2030 funding. Also of course you could email the GM.
I generally do not receive a response to emails I send to the GM.
Thank you for this comprehensive history of the last decade of development efforts in the Central Area.
With respect to your categories “Community Conversations” and “Lack of . . . Comprehensive Member Survey,” it is more than a little interesting to read on the Oakmont 2030 page at oakmontvillage.com what the preferred AIA Communities by Design plan was for Oakmont 2030 before AIA had to be abandoned because of Covid and the project was totally revised — note the time expected to be devoted to each segment and note especially what was to be Phase 2 – Outreach and Data Collection:”
https://oakmontvillage.com/2030-2/
“How will this work?
Phase I (Date TBD)
The AIA sponsored virtual kick-off meeting to introduce the Communities by Design program, their philosophy, their work with other communities and their process moving forward.
Phase Two: Outreach & Data Collection
The AIA will conduct a 6-week outreach campaign consisting of a community-wide survey.
Phase 3: Community Workshop (Date TBD)
The AIA will host a 90-minute online community workshop with Oakmont residents to collect information on community aspirations and values. The workshop, in combination with the survey findings, will inform the team’s work.
Phase 4: Team Studio Work & Community Presentation
A week after the workshop, the AIA Team will provide a community presentation to share its findings, observations and recommendations to the Oakmont community, followed by a question-and-answer session.
Phase 5: Panel Discussion (Date TBD)
The AIA team will host a virtual panel session to get Oakmont resident’s reaction to a masterplan that will be developed by Archilogix and presented to the community.”